When do I have to order? Count it backwards
Enter the date you need the goods in your warehouse and where they are shipping to. The calculator counts backwards through customs, sea freight, production and the sampling round, and tells you the last date the order has to be confirmed.
Counted with the Ramadan order deadline calculator — Hala Deco, Yiwu.
How the arithmetic works
| Production | 40 days, counted from deposit received and artwork approved — not from the enquiry |
|---|---|
| Sea freight | 12–38 days depending on destination; the values in the list are typical, not a sailing schedule |
| Customs + inland | about 7 days — change it if your port is slower |
| Sampling (custom only) | about 10 days for samples and artwork approval, and it runs before the 40-day production clock starts |
| Flat-packed by default | Ornaments ship flat and unassembled, which lowers carton volume and freight; assembled packing is available on request |
These are planning dates, not a commitment — the dates we commit to are the ones on your quotation. If your season is fixed, tell us the date you need the goods and we will say what is realistic before you order rather than after. See the Ramadan 2027 ordering calendar for the full season view.
Put this calculator on your own site
If you publish for importers — a sourcing blog, a buying group, a freight newsletter — you can embed it. Copy the code below; it needs no account and sends nothing back to us.
Building a Ramadan & Eid order?
Send the quantities and your destination port — we will come back with pricing, samples and a loading plan.